Discussion:
Members considered a report
regarding a call-in received from eight Members of the Council
regarding the Cabinet decisions taken on 26 July 2022 on the Future
Hoo Progress Report.
Councillor Mrs Turpin, as the
lead call-in Member, explained the reasons for the call-in, as set
out in paragraph 2.12 of the report to the Committee. She noted
that
- at the Cabinet
meeting on 26 July, several changes had been made to the Medway
Infrastructure Delivery Plan (Appendix 5 to the Cabinet report),
however, she did not believe the revised figure agreed at the
meeting was correct.
- all the additional
rail infrastructure funding had been removed, queried therefore how
a functioning railway station could be delivered. Removing the
highways funding lines did not mean that these projects were no
longer required
- the sports centre
delivery was in question,
- health and social
care funding estimates had been removed, but the point was made
that these were still needed to give an indication of what could
actually be delivered.
- the purpose of the
HIF was to have the infrastructure in place before housing was
built. The funding was now uncertain, given the significant
reliance on S106 contributions and the fact that in many areas
funding sources were still to be determined. Without more certainty
around funding it seemed unwise at this
point to go out to consultation.
Other Members who had called in
the decisions made the following points:
·
It was unclear whether the HIF project was on track
financially
·
Whilst the proposed projects in
theInfrastructure Delivery Plan (IDP) were
welcomed, whether they could be funded was a significant
concern
·
The validity of the documents agreed by Cabinet was
questioned
·
There were concerns about the removal of the
budgetary pressure for passenger subsidies, given the need to
identify funding for the railway station
·
The removal of the funding set aside for the Hoo
Peninsula Road additional costs, including contingency, was a
concern given high inflation and the impact on construction
costs
·
There was a need for certainty as to whether
projects could still be delivered given the changes made by Cabinet
to Appendix 5
·
There had been insufficient engagement with local
Members
·
There was too much reliance on S106 contributions
and greater clarity was needed, particularly as elements of this
were higher risk and the amounts being sought were higher than
usual
·
Cabinet had set aside feasibility funding in 2018 to
allow detailed consideration of a possible sports centre, but no
work seems to have taken place, even though the present sports
centre was not adequate.
The Director of Place and
Deputy Chief Executive apologised to Members for the issues with
Appendix 5 of the Cabinet Report in particular, acknowledging that
whilst these were complex matters, the information should have been
made clearer. Responding to the points raised by members of the
Committee;
·
that Cabinet Members had not had enough time to read
the amended papers after the adjournment, he noted the changes to
Appendix 5 had been requested by Members and Cabinet had simply
needed to assure itself these changes had been incorporated;
indeed, the Leader had gone through them at the meeting in detail.
Further, Appendix 5 was not the document subject to consultation
and thus not one for a decision by Cabinet.
·
The IDP was a requirement under national Planning
policy, which recognised that there may not be certainty or the funding secured for the necessary
strategic infrastructure at the time the plan was produced. This
point was reiterated in the IDP itself and
also seen in other Councils’ IDPs. Members had rightly
pointed out additional funding was required, but that was
countenanced under national planning policy. It would be virtually
impossible to finalise, quantify and secure funding such a long
time in advance and the IDP would continue to evolve over
time.
·
With regard to
the HIF, these projects would be able to be
constructed within the funding envelope agreed with Homes England.
There were significant cost pressures which were impacting on the
construction sector. The Council’s housing target in 2016,
before HIF, was 30,000. HIF funding had been secured through a
competitive process which allowed the Council to forward fund core
infrastructure projects. Without HIF these would have to be funded
by developer contributions, which could only go so far and if spent
on core infrastructure could not also be spent on community
facilities, such as health and education. With or without HIF the
housing target remained at 30,000 homes and some form of housing
development on the peninsula was inevitable.
The Committee then debated the
call-in and the following issues were discussed:
- Changes made to
the Infrastructure Delivery Plan- some
Members considered that the revised Appendix 5 still contained
serious errors. In terms of funding which needed to be identified,
£100m had been removed from Table 1A in Appendix 5 and
clarity was requested on costings so that people on the peninsula
could see whether what was being consulted on could be delivered.
Officers explained in detail, on a line-by-line basis, why each
change to the Infrastructure DeliveryPlan had been
made.
- Explanatory
document –
Members suggested that an additional document should
be produced to clearly explain the key elements of the Hoo
Development Framework and how they will be funded, including
current uncertainties and the assumptions that had been made around
S106 contributions. This would assist Members when engaging with
residents. A point was made that the process needed to be more
transparent with greater Member involvement.
- Budget and Policy
Framework considerations – the Monitoring Officer assured
Members that the Cabinet decisions were not a breach of the Policy
Framework. The latter was defined in the Constitution and included
the Local Plan (referred to as the Development Plan). The
Consultation document did not breach any of the policies which
comprised the Policy Framework.
- Hoo Development
Framework (HDF) –
officers advised this was at an early stage and was
an attempt to show what sustainable development for the peninsula
looked like. In the absence of a Local Plan, concerns about
delivery were understandable but the document was not a wish list
and had been developed in consultation with stakeholders and
providers, and at this stage there could not be certainty about
costings. Members were assured that the HDF was a part of the
evidence base for the Local Plan, which would continue to be
developed.
- Members questioned
why consultation on the HDF had to happen now when it was dependant
on the HIF being delivered, which was not certain. The weight the
approved document would be given in the absence of a Local Plan was
also queried. The Head of Planning advised that it was now the
right time to go out to consultation to set out the wider context
for the HIF projects, as requested by residents. The HDF was a
consultation document which forms part of the evidence base for the
Local Plan.
- Members queried what
would happen if developers submitted planning applications for Hoo
on the basis of the existence of the HDF
when the evidence base was not there yet. The Head of Planning
commented that developers understood the situation and were holding
back on submitting large planning applications. Any applications
made before the Local Plan was adopted would be assessed on its
merits. With HIF in place, applications would be more sustainable.
Without HIF, S106 contributions would need to go towards the costs
of infrastructure.
- Committing future
Administrations to policies – the point was made that it
should be possible to give some guidelines as to what was expected
of future Administrations.
- S106
Contributions –
whether these would need to substantially increase
to pay for the projects in the Infrastructure Delivery Plan was
queried. Officers advised that the IDP was developed on an
iterative basis, that built on past
experience in securing S106 contributions and would evolve
as the evidence base was gathered. The IDP made clear that only
infrastructure required in the first 5 years must be shown to be
deliverable. There was a need to be clear about aspirations, but it
was not possible to provide certainly over 20 years of development
at this stage of the process. The Head of Planning confirmed there
would need to be an uplift in S106 contributions, which would fund
significant elements of the infrastructure, but other funding would
still need to be identified.
- Rail Service
offer – how to future proof this to allow the Medway curve to be built
in the future was queried. Officers advised that the rail service
proposed was deliverable and enabled the service to grow as the
community grew. Initially, there would be a battery operated two
carriage train capable of carrying 120 passengers. The impact on
existing freight services was a constraint but the tracks existed
already and were being tested to make sure they could deliver the
expected passenger service. Officers advised the design of the
service would not preclude the Medway curve in the future. Whether
the land needed for the Medway curve was in Council or third-party
ownership would be clarified. It was pointed out that Network Rail
had signed up to the Council’s proposals. Members expressed
surprise at the response that the three transport projects that had
been removed had never been part of what had been agreed with Homes
England in terms of HIF funding and were for the Council to decide
on at a later date. The fact these
elements were aspirational had not been made clear.
- Governance around
the Local Plan – concern was
expressed at the lack of wider Member involvement in the
development of the Local Plan, with insufficient time for Members
to make informed decisions.
- HIF
project– in response to how much
was left of the £170m allocated, Members were advised that an
annual budget was prepared and monitored quarterly. To date
£10m had been spent, which had helped to provide considerable
certainty for the project, involving consultations, due
diligence and wider planning for the
scheme. A Member queried this figure on the basis £6m had
been budgeted for delivery. Officers advised the delivery budget
was not overspent, and spend on highways
etc would be allocated to the relevant element of the budget and
not against the delivery budget. Officers advised that every claim
for the costs of HIF projects had to be approved by Homes
England.
It was proposed that the
decisions be referred back to Cabinet
for reconsideration with a recommendation that a new, concise
document be produced as part of the consultation process to enable
a better understanding of the wider issues in the Hoo Development
Framework. Although this was agreed, due to concerns that not all
Members had fully understood the scope of the new document being
recommended, there was an adjournment so that the exact wording
could be formulated and put to the Committee.
Following the adjournment,
Members were advised that if the Committee considered the decision
had not been fully understood by all Members then it was open to the Committee to rescind
its decision. Following a vote, the Chairman announced that the
decision to refer the matter back to Cabinet had been
rescinded.
It was then proposed that the
Cabinet decisions be referred to Council. The Monitoring Officer
advised that the Committee would need to
decide that it had considered the advice from the Monitoring
Officer and the Chief Operating Officer that the Cabinet decisions
were not outside the budget or policy framework, and had decided to
disagree with that advice.
The proposal that the decisions
be referred to Full Council was agreed.
Decision:
The Committee agreed to refer
the Cabinet decisions to Council for consideration.