Discussion:
This report presented the
annual review of the Highway Infrastructure Contract between Medway
Council and VolkerHighways. This
covered the period from August 2020 to July 2021. The contract had
commenced in 2017 for a period of five years, with the possibility
of five single year extensions, depending on performance.
VolkerHighways had achieved the level
required for a third year extension
which meant that the contract was currently scheduled to end on 31
July 2024.
It was noted that the
maintenance of the highway and its assets was a statutory duty and
that the current value of the highways assets was just over
£2 billion with the land being valued at just under £3
billion. The intention was for the next annual update to be
reported to the Committee in January 2023.
The following was
discussed:
- Highways Funding
– A Committee Member expressed
concern that highways funding provided by the Department for
Transport was reducing year on year and that there was a shortfall
in Medway. The Acting Head of Highways responded that there was
reduced funding available nationally. Covid-19 had been a factor
and it was not yet clear how funding would recover. She advised
that there had been no reduction in the revenue or capital budget
available until the current year. The maintenance of infrastructure
would be a challenge in view of the funding constraints. Funding
was prioritised to ensure highways were kept in a safe condition,
which was a statutory duty. Remaining funding would be targeted to
achieve the best outcomes possible. Over the last few years,
investment had been targeted at the unclassified network. This had
ensured that the national average had been met for classification.
Although 17% of unclassified roads still needed maintenance,
improvements had been made by using available resources
effectively. The amount of funding required nationally was so large
it was not clear how it would be resolved in the long term. The
funding deficit for maintenance had reduced from around £41
million to £32 million.
- Designated design
life – It was confirmed that there
was not a list of designated design life for every carriageway and it was not known when every
carriageway had been built. A rolling programme of condition
surveys was undertaken for the full road network and the structural
condition of every road was monitored. There was awareness of the
maintenance backlog but securing the funding required was
challenging.
- Electric Vehicle
Fleet – A Member asked when 100% of
the vehicle fleet would be electric. The Acting Head of Highways
said that there were currently three electric vehicles in the fleet
and that alternative fuel sources were being considered. The
VolkerHighways representative added
that battery technology and vehicle range was not yet good enough
for use in larger vehicles. Vehicles were being trialled on an
ongoing basis.
- Medway Tunnel
– In relation to the Medway Tunnel
and Road Infrastructure Scheme, it was asked how the £4.9
million of funding was broken down. The Acting Head of Highways
said that the final programme was currently being put together
ready to go out to tender. Much of the funding would be used within
the tunnel but there would also be a retaining wall in Pier Road
and the road linkages to the tunnel would be improved. A breakdown
of the expenditure would be circulated to the Committee following
the meeting. In response to a further question, it was confirmed
that Challenge Fund money had to be spent by 2024 and plans were
currently on track to meet this, although there were a number of challenges, such as sourcing materials.
A Life Cycle Plan would be run in relation to the Medway Tunnel so
that the impact of the money invested could be
ascertained.
- Highways
Infrastructure Funding (HIF) – in
relation to the HIF for the Hoo Peninsula, the new roads would need
maintaining and new housing would require the construction of
further roads. The Member requested the undertaking of a
Sustainability Appraisal for the HIF and questioned how the
maintenance costs of these extra roads would be funded. In
response, the Acting Head of Highways said that HIF was not
delivered out of highways funding. She said that roads were only
adopted once they met certain criteria, which ensured that good
quality assets were adopted. The Department for Transport Funding
formula was based upon road length, but new roads would not attract
much extra funding as they represented a small percentage of the
overall network. There was a need to maximise the use of existing
resources and bid for any new resources available.
The
Director of Place and Deputy Chief Executive added that as
regeneration progressed there would be additional roads requiring
maintenance but quality was assessed
prior to the adoption of the roads. HIF would see £86 million
of expenditure on roads and the Council would want to ensure that
roads were built to a high quality to ensure longevity. Funding
from the DFT for the existing road network needed to be considered
as well as developer Section 106 contributions. The Council’s
Asset Management approach would be adopted. This was ongoing work
and while there would not be enough funding to do everything, the
approach was about maximising use of resources and opportunities
for funding, ensuring that all work undertaken was to a high
standard to ensure longevity. The Assistant Director, Regeneration
added that everything would be built to a suitable standard for
adoption.
- Flooding and
Drainage – A Member asked for an
update about the ongoing flooding issue and the resulting
congestion near to the Asda store in Pier Road. The Acting Head of
Highways considered that headway was being made with Southern Water
in addressing the issue but that it required significant
expenditure. There was now a better understanding of the issue.
Highways were engaging with Southern Water but work to address the
issue was not understood to be imminent. A further update would be
provided to the Committee outside the meeting.
Decision:
The Committee:
a)
Noted the contents of the report and the Annual
Review for Year 4 of the HIC, as set out in Appendix 1.
b)
Requested that a breakdown of the £4.9 million
of Department for Transport Challenge Funding be provided to the
Committee, with particular reference to
the amount to be spent on the Medway Tunnel
improvements.
c)
Requested that an update be provided to the
Committee in relation to the addressing of flooding and drainage
issues in the vicinity of the Asda store in Pier Road,
Gillingham.