42/2007 The Cabinet approved the separation of
disposal services from collection services as the outcome of the
former has an impact upon the options for the latter.
43/2007 The Cabinet approved the adoption of Option 2, as set out
in the report, with the disposal of waste being dealt with in
advance of other waste services.
44/2007 The Cabinet noted the need for a further Options Appraisal
paper in respect of waste collection options to be submitted at the
latest by the time the disposal options reach the contract award
stage at Gateway 3.
45/2007 The Cabinet agreed that subject to compliance with EU
procurement regulations and best value rules, the procurement
arrangements will be undertaken so as to ensure the Council is
fully able to benefit from economies of scale should the disposal
and, later, the collection contract be awarded to the same
contractor.