Gateway 1 Batched Procurement Commencement: Abbey Court School, Elaine Primary School, Twydall Primary School - Building Projects

Meeting: 02/08/2011 - Cabinet (Item 13)

13 Gateway 1 Batched Procurement Commencement: Abbey Court School, Rainham, Elaine Primary School, Strood, Twydall Primary School, Gillingham - Building Projects pdf icon PDF 61 KB

Minutes:

Background:

 

This report sought permission to commence the batched procurement of building works at Abbey Court School in Rainham, Elaine Primary School n Strood and Twydall Primary School in Gillingham. 

 

It was noted that the costs of the Abbey Court project would be met from the SEN Programme, the Elaine project from the Basic Need Programme and the Twydall project from the Primary Capital Programme.

 

The report considered the options available and recommended procurement via a below EU Threshold Select List. An exempt appendix set out details of the whole life costings and budget for the projects.

 

It was noted that the Strategic Procurement Board had considered and recommended this report to Cabinet on 6 July 2011.

 

An exempt appendix provided the detailed finance and whole-life costings information for the building projects.

 

Decision number:

 

Decision:

101/2011

The Cabinet approved the Abbey Court School, Elaine Primary School and Twydall Primary School projects to proceed to Gateway 2 of the procurement process and invite tenders for the schemes of works, on the basis set out in paragraph 3.9 of the report (Procurement via a below EU Threshold Select List).

 

Reasons:

 

The projects will support the delivery of the required improvements to Abbey Court, Elaine and Twydall Schools, within the required timeframes and budgets.