Gateway 1 Options Appraisal: All Faiths Children's Community School Building Project

Meeting: 15/02/2011 - Cabinet (Item 13)

13 Gateway 1 Options Appraisal: All Faiths' Children's Community School Building Project pdf icon PDF 323 KB

Minutes:

Background:

 

This report set out the options appraisal for the project at All Faiths Children’s Community School in Strood.

 

It was noted that the project supported the Council’s strategy to provide improved accommodation for the school and Children’s Centre, which was currently insufficient to deliver the curriculum for its pupils; including 22 children with statements of special educational needs for significant hearing impairment using a total communication approach.

 

An exempt appendix set out details of the whole life costings/budget, fees payable and risk register for the project at All Faiths Children’s Community School.

 

The Procurement Board had considered this report on 19 January 2011 and had supported the recommendations as set out.

 

Decision number:

Decision:

34/2011

The Cabinet approved the project to proceed to Gateway Two – Competitive Process, on the basis set out in paragraph 7.3.1 of the report (JCT Standard Form of Contract).

 

Reasons:

 

The new facilities are required to enable the school to deliver the quality of curriculum offered for the key subjects as described in the business case section of the report. The capital programme approved in February 2010 included funding for the project.