Gateway 1 Options Appraisal: Building Works for Napier Community Primary and Nursery School

Meeting: 08/03/2011 - Cabinet (Item 5)

5 Gateway 1 Options Appraisal: Napier Community and Nursery School Building Project pdf icon PDF 59 KB

Minutes:

Background:

 

This report sought permission to commence the procurement of building works at Napier Community and Nursery School in Gillingham.

 

It was noted that Napier was one of the schools identified as a priority to receive funding as part of the Council’s Primary School Capital Programme and that this project supported the Council’s strategy to provide improved accommodation for the school and create one facility for the pupils, families and local community.

 

The report considered the options available and recommended procurement via an EU compliant framework. An exempt appendix set out details of the whole life costings and budget for this project.

 

It was noted that the Strategic Procurement Board had considered and recommended this report to Cabinet on 16 February 2011.

 

Decision number:

Decision:

43/2011

Cabinet agreed that this project proceed to Gateway 2 of the procurement process and tenders be invited for the scheme of works, on the basis set out in paragraph 3.9 of the report (Procurement via a below EU Threshold Select List).

 

Reasons:

 

The decision and project will support the delivery of the required improvements to Napier School, within the required timeframe.