Additional documents:
Minutes:
Background:
The report presented performance in Quarter 1 (Q1) & Quarter 2 (Q2) 2024/25 on the delivery of the One Medway Council Plan (OMCP) 2024/28 which set out the Council’s priorities and performance indicators, as well as the Q1 & Q2 2024/25 review of strategic risks, all of which would also be presented to the Council’s overview and scrutiny committees.
Summaries of the OMCP performance indicators were set out in Appendix 1 to the report, with the Strategic Risk Summary set out in Appendix 2 to the report.
number:
|
Decision:
|
The Cabinet noted the Q1 and Q2 2024/25 progress of the performance indicators used to monitor progress of the Council’s priorities, as set out in Appendix 1 to the report. |
|
150/2024 |
The Cabinet agreed the Strategic Risk Summary, as set out in Appendix 2 to the report. |
Reasons:
Regular monitoring of performance and risks by management and Members is best practice and ensures achievement of corporate objectives.