Background:
This report detailed the options relating to the delivery of the One Public Estates (OPE) Brownfield Land Release Fund (BLRF) enabling works Contract. This was to facilitate the delivery of a minimum of 164 residential units at the Mountbatten House building.
The report proposed that Medway Development Company (MDC) be contracted to deliver the works to bring forward the site.
Decision number:
|
Decision:
|
49/2023 |
The Cabinet agreed:
i) The preferred option of a direct award as identified in paragraph 6.3.1 of the report (direct award to Medway Development Company.)
ii) The award of services/works for the cost. |
Reasons:
The appointment of MDC as Project Manager and Contractor to deliver the enabling works for the OPE BLRF, would ensure completion of the project and the utilisation of grant funding.