5 Splashes Leisure Centre PDF 175 KB
Minutes:
Background:
The report advised that should approval be given for the demolition of the existing facility, a further report would be presented to a future meeting of the Cabinet in relation to the business case and any further capital addition required.
Decision: |
|
56/2021 |
The Cabinet approved the demolition of the existing Splashes Leisure Centre building, Option 2 of the report, to allow for a future Leisure facility on that site. |
57/2021 |
The Cabinet agreed that the demolition costs of £343,000, inclusive of professional fees, are funded from the existing £5 million capital scheme, Splashes Refurbishment 2020/21, to enable the demolition of the existing Splashes Leisure Centre building for future development on that site. |
58/2021 |
The Cabinet agreed that the existing Splashes scheme, Splashes Refurbishment 2020/21, be renamed Splashes Replacement. |
Reasons:
To enable the demolition of Splashes Leisure Centre and remove the risks of building collapse, vandalism / anti-social behaviour and ongoing maintenance costs.