Issue - meetings

Capital Budget Monitoring

Meeting: 27/09/2005 - Cabinet (Item 4.)

Capital Budget Monitoring

Decision:

208/2005 The Cabinet noted that:
Spend on the approved programme since 1 April 2005 to date amounted to approximately £16 million;
Forecast spend during 2005/2006 as a whole amounted to £77 million;
The virements within the existing programme detailed in section 8 of the report.
209/2005 The Cabinet agreed to recommend the proposed additions to the capital programme, described in section 7 and detailed in Appendix 6, to Council for approval.
210/2005 The Cabinet approved the virements to establish the provision of temporary accommodation for sixth form places as described in sections 5.2 and 8.2 of the report.