Gateway 4 Procurement Contract Review: Housing Revenue Account (HRA) Development - Garage Sites

Meeting: 09/02/2016 - Cabinet (Item 18)

18 Gateway 4 Procurement Post Project Completion Review: Housing Revenue Account (HRA) Development of Garage Sites for Additional Housing Stock pdf icon PDF 76 KB

Minutes:

Background:

 

This report provided details of the performance of the contract awarded for the delivery of the first work stream for the construction of 23 affordable homes on a total of 10 locations in Medway, 9 of which were disused garage sites previously owned by the Housing Revenue Account (HRA).

 

An exempt appendix provided key information in respect of the financial analysis for the contract.

 

Decision number:

Decision:

The Cabinet noted the performance of the Housing Revenue Account (HRA) Development Garage Sites and achievement of the outputs described in sections 2 and 4 of the report.

 

Reasons:

 

The contract, which started in July 2014, has successfully delivered the programme of works.