6 Capital Budget Monitoring - Quarter 3
PDF 135 KB
Minutes:
Background:
This report and accompanying appendices gave details of the capital monitoring position for the period to December 2013 (the end of the third quarter), with a forecast outturn for 2013/2014.
The approved capital programme for 2013/2014 and future years was £98.5 million, consisting of £41.6 million in respect of brought forward schemes and £56.8 million of new approvals.
The report commented on the delivery of the capital programme and updated Members on a number of issues. The current forecast showed that £51.033 million of the programme was forecast for spend during 2013/2014.
The Cabinet accepted this report, as set out within Supplementary Agenda No. 2, as urgent to enable Members to receive and consider the latest budget information at the earliest opportunity.
|
Decision number: |
Decision: |
|
|
The Cabinet noted:
(a) the spending forecasts summarised at table 1 of the report; (b) the new approvals outlined at paragraph 4.3.1 of the report authorised under officer delegations. |
Reasons:
Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.