11 Gateway 1 Procurement Commencement: Greenvale Infant School Phase 3 PDF 283 KB
Minutes:
Background:
This report sought permission from the Cabinet to approve the commencement of the procurement process for a new build extension for the entrance and administration and a review of the existing accommodation to allow for two extra classrooms at Greenvale Infant School, Chatham.
The Procurement Board considered this report on 23 July 2013 and recommended that Cabinet approve the commencement of the procurement process.
An exempt appendix contained finance and whole-life costings information for this project.
Decision number: |
Decision: |
137/2013 |
The Cabinet approved the commencement of the procurement process at Gateway 1 on the basis set out in paragraph 3.10 of the report, for progression to Gateway 2 of the procurement process and invite tenders for the building works. |
Reasons:
The refurbished accommodation is required to enable the school to expand by 2FE. The budget for these works was approved by Cabinet on 12 June 2012 (decision 85/2012).