This report provided details of the development of this project since the Cabinet report of 24 August 2009 with an update on the first stage contractor’s performance (Contract Management Gateway 4) and a recommendation for the appointment of the contractor for the main works (Contract Award Gateway 3).

 

The Cabinet accepted this as an urgent item to enable the contract for the main works to be let and to commence as soon as possible.

 

Decision number:

Decision:

50/2010

The Cabinet agreed to authorise the Director of Children and Adult Services, in consultation with the Portfolio Holder for Children’s Services, to appoint Mansells as the second stage contractor for the main works.

 

Reasons:

This enables the project to proceed at the earliest opportunity. Delay to the project at this time will mean additional cost being incurred, continued occupation of temporary accommodation by the school, delay in commencement of works, and associated delay to completion.