Decision Maker: Cabinet
Decision status: Decision made
Is Key decision?: Yes
Is subject to call in?: Yes
To seek approval to the revised proposals for
the revised dynamic bus facility.
Relevant Overview and Scrutiny Committee: Regeneration, Community
and Culture
194/2009 The Cabinet agreed that (a) a
planning application be submitted for a revised scheme (as
described in this report, and as shown in the sketches appended to
it). (b) the loss of existing public open space in the proposed
site be advertised in the local press in accordance with s123 (2A)
of the Local Government Act 1972 and the Director of Regeneration,
Community and Culture be delegated authority, in consultation with
the Portfolio Holder for Community Services, to consider any
objections and determine whether or not to appropriate the land.
(c) these decisions are considered urgent and therefore should not
be subject to call-in.
In order to progress proposals for the Dynamic
Bus Facility as part of the ongoing regeneration programme in
Chatham.
Publication date: 24/11/2009
Date of decision: 24/11/2009
Decided at meeting: 24/11/2009 - Cabinet
Effective from: 03/12/2009
Accompanying Documents: