Decision details

Gateway 3 Contract Award: A228 Fenn Corner

Decision Maker: Cabinet

Decision status: Decision made

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To consider the contract award for the Fenn Corner Roundabout.

Relevant Overview and Scrutiny Committee: Regeneration, Community and Culture

Decision:

235/2009 The Cabinet agreed to accept the tender from Raymond Brown Construction, as set out in the exempt appendix, subject to receipt of planning consent and completion of the land transfer agreement.

Reasons for the decision:

This decision is required so that the project can proceed to the construction phase.

Publication date: 15/12/2009

Date of decision: 15/12/2009

Decided at meeting: 15/12/2009 - Cabinet

Effective from: 24/12/2009

Accompanying Documents: