Acceptance of Tender - Chatham Town Centre Traffic Scheme

Decision Maker: Cabinet

Decision status: Decision made

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The report will outline the works proposed in phase 1 of the Chatham Centre Traffic Scheme and seek authority to accept a tender or tenders subject to funding for the project receiving approval from ODPM.

Decision:

252/2005 The Cabinet accepted the tender from Carr Construction on the terms set out in the exempt appendix to the report subject to the approval of funding by the ODPM.
253/2005 The Cabinet authorised the Director of Regeneration and Development to issue a Letter of Intent to Carr Construction to enable detailed programme planning to take place.

Reasons for the decision:

The reconfiguration of the road network and the award of this tender is essential to the delivery of the Chatham Centre and Waterfront Development Framework.

Publication date: 08/11/2005

Date of decision: 08/11/2005

Decided at meeting: 08/11/2005 - Cabinet

Effective from: 17/11/2005