Capital Monitoring 2003/2004

Decision Maker: Cabinet

Decision status: Decision made

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

This report presents the capital monitoring for the period to December 2003, with an outturn forecast for 2003/2004. The report comments on the delivery of the capital programme, variations to the approved programme, and updates on key issues.

Decision:

The Cabinet noted:·Spending on the approved budget amounted to approximately £26.6m;·The completed schemes and the outputs that have resulted (section 5.1 of the report);·The progress of
arger specific schemes contained in section 5.3 of the report;·
The proposed use of capital resources available to fund the programme, as referred to in table 3 of the report.




The Cabinet recommended the proposed addition to the capital programme, summarised in table 2, to Council for approval.

Reasons for the decision:

Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.

Publication date: 17/02/2004

Date of decision: 17/02/2004

Decided at meeting: 17/02/2004 - Cabinet

Effective from: 26/02/2004