Decision Maker: Cabinet
Decision status: Decision made
Is Key decision?: Yes
Is subject to call in?: No
This report set out the details of the Council’s contract for the Decent Homes Programme 2010/2011. An exempt appendix provided the anticipated value of works. The Council was required to ensure that 100% of its housing stock met decent homes standards (set by government) by December 2010. Awarding the 2010-11 Decent Homes works as recommended would ensure that this target would be achieved.
It was noted that the Procurement Board had considered the report on 9 June 2010 and supported the recommendations as set out in the report.
Decision number: |
Decision: |
86/2010 |
The Cabinet agreed to continue the 2010/2011 Capital works under its existing contract with Mears, on the basis of the discount on their existing contract rates. |
87/2010 |
The Cabinet agreed that the Monitoring Officer may grant a waiver to Contract Rules to continue with the existing consultant project team on their existing tendered rates. |
88/2010 |
The Cabinet delegated authority to the Assistant Director, Housing and Corporate Services, in consultation with the Portfolio Holders for Finance and Housing and Community Services, to agree a further discount with Mears for ongoing capital works that may be required following the completion of the Asset Strategy and subsequent capital programme of works. |
Reasons:
· To ensure Decent Homes target is achieved by the December 2010 deadline.
· To maintain continuity of works and maximise value for money using the existing tendered contract.
· To continue to build the trust and confidence of tenants now that the decent homes programme has recommenced.
· To retain a high performing principal Contractor and project team.
· To mitigate risk issues in relation to the existing Mears Contract.
Report author: Jim Mack
Publication date: 11/10/2010
Date of decision: 29/06/2010
Decided at meeting: 29/06/2010 - Cabinet