Decision Maker: Cabinet
Decision status: Decision made
Is Key decision?: Yes
Is subject to call in?: Yes
To seek approval to commence the procurement
process for the the provision of the new Stoke Crossing
(A228).
Relevant Overview and Scrutiny Committee: Regeneration, Community
and Culture
234/2009 The Cabinet agreed to: (i) approve
the line and layout of the new road and bridge as set out in the
drawings appended to the report and the preferred options
(paragraph 7.11 of the report); (ii) approve the use of weathered
steel for the main beams; (iii) a planning application for the
bridge being submitted; (iv) note that the Monitoring Officer had
agreed the use of the Accelerated Restricted Procedure under her
delegated authority, and in consultation with the Procurement
Board; (v) delegate the decisions to the form of the contract to
the Monitoring Officer in consultation with the Procurement
Board.
These decisions enable the project to be
progressed and delivered in accordance with the signed Community
Infrastructure Funding agreement, minimise future maintenance costs
and enable officers to make timely decisions in the best interests
of project delivery based on the final design and its
costs.
Publication date: 15/12/2009
Date of decision: 15/12/2009
Decided at meeting: 15/12/2009 - Cabinet
Effective from: 24/12/2009
Accompanying Documents: