Decision details

Chatham Road Network: Flyover Demolition and Construction of Bus and Taxi Route - Contract Award

Decision Maker: Cabinet

Decision status: Decision made

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

This report seeks the approval to the award of a contract the demolition of the flyover at Sir John Hawkins Way, Chatham and the subsequent construction of a bus and taxi route

Decision:

259/2008 The Cabinet accepted the tender from Breheny as set out in the exempt appendix.

Reasons for the decision:

This decision is required so that the programme of works to deliver the regeneration of Chatham can proceed.

Publication date: 16/12/2008

Date of decision: 16/12/2008

Decided at meeting: 16/12/2008 - Cabinet

Effective from: 26/12/2008

Accompanying Documents: